Wednesday, July 13, 2005

Energy walls started!


Another pic of Maeve holding my camera case.

More ductwork went in today, and the energy walls were started. And finally the plumber can finish his job putting the shower in. That got delayed because the wall needed to be insulated and finished correctly.

Unfortunately the fireplace got framed incorrectly, so that might get delayed a couple days. We used the brochures dimensions, which shows the finished product, where we should've used the insulation instructions (which they never gave me...)

Energy wall should be finished tommorrow, so hopefully the plumber and HVAC guys can get finished early next week, and pass inspections. My uncle and I are intending to spend Tuesday out there to finish our work, and get the basement wired.

Comments: Post a Comment

Subscribe to Post Comments [Atom]





<< Home

This page is powered by Blogger. Isn't yours?

Subscribe to Posts [Atom]